Stocks in play: Ero Copper Corp.

Baystreet - Wed Jun 12, 8:43AM CDT

Has received the Operational License for the Tucumã Project – the last remaining permitting milestone for commercial operation. With physical completion at approximately 99%, commissioning well advanced, and over 90% of the operational staff hired and trained, first concentrate continues to be expected early in the third quarter of 2024. The total direct capital cost estimate for Project completion remains unchanged at approximately $310 million. Ero Copper Corp. shares T.ERO are trading unchanged at $27.85.